Government

Widening and other improvements will begin soon on the oldest part of Interstate 95 in North Carolina

By Staff Report, posted 3 years ago
The map above indicates the general location of the project. Photo provided by NCDOT

The N.C. Department of Transportation announced Thursday that a $236.5 million contract has been awarded for upgrades on the 9-mile stretch of highway from north of Exit 71 in Harnett County to Interstate 40 in Benson. Two lanes will be added in each direction, bringing the total to eight on the section, which opened in 1959.

The contract was awarded to a joint venture of Flatiron and Fred Smith Co. based in Morrisville. The scope of work will be identical to the widening underway on I-95 from just north of Exit 55 in Cumberland County through Exit 71, which is being reconstructed south of Dunn, according to a news release from the NCDOT.

Early work on the project -- which could begin as early as Aug. 30 -- will require overnight lane closures so the contractor can add temporary pavement and concrete barriers.

The contractor has until the summer of 2026 to complete the project. The widening and upgrades south of Dunn are scheduled to be completed in the summer of 2024.

The upgrades include improving culverts so water can safely flow underneath the interstate, which has seen flooding in closures in recent hurricanes.

Meanwhile, the NCDOT said an I-95 widening project south of Fayetteville has been delayed. The upgrades to a 9-mile stretch between mile marker 13 and exit 22 in Robeson County won’t begin until next year.

Spokesperson Andrew Barksdale told The Robesonian newspaper that “very complex design elements” and other requirements caused the DOT to delay accepting construction bids. The bidding that was originally set to open in June is now scheduled to open Sept. 21, Barksdale said.

The project includes adding two lanes in each direction (bringing the total to eight), as well as interchange upgrades and bridge replacements. Work is expected to be completed in 2026.

The work on I-95 in the Fayetteville region -- all of which is funded -- is part of ongoing efforts to widen and modernize the busy interstate.

According to the NCDOT’s website: “The 182-mile stretch of Interstate 95 in North Carolina was built between the late 1950s and 1980 as a four-lane interstate highway. There have not been any large-scale improvements or widening.”

The NCDOT also announced Thursday that a route near the Cumberland-Robeson county line will close Monday for two months as work continues on the new Fayetteville Outer Loop.

The contractor is closing a portion of Leeper/Parkton Road north of N.C. 71 as part of the construction of a 6-mile segment of Interstate 295.

Signs will direct motorists to detour along Natural View Drive, U.S. 301 and N.C. 71. The 6-mile segment is scheduled to be completed in 2023.

Ico insights

INSIGHTS

SPONSORS' CONTENT

In The Current Issue

Tech for a cause: 2025 Tech ID Day showcases new innovations while supporting warfighters and a good cause

To wrap up the first day, attendees were able to meet up for a social event at the Brad Halling American Whiskey Ko. in Southern Pines where a $10,000 check was presented to the Joint Special Operations Foundation for their scholarship fund. Photo pr


Gathering great ideas: Business incubator coming to the 400 block of Hay Street

The three-story, 200,000 square-foot business incubator space is located at 420 Maiden Lane. The building features an elevator, construction has begun on handicap bathrooms for the first floor and the second and third floors feature window walls offering views of Segra Stadium.


Planting seeds of H.O.P.E: FTCC's Hope, Opportunity, Prosperity through Education Program provides empowerment through hands-on learning

Image provided by FTCCFocused on building the local workforce and streamlining the education process through real world learning, the Hope, Opportunity, Prosperity through Education Program at Fayetteville Technical Community College (FTCC), also kno