A highway outside Pembroke will close for about two months starting next week for the construction of a roundabout.

A contractor will close the intersection of N.C. 710 and Deep Branch Road starting at 7 a.m. on Monday. The intersection is scheduled to open by late November.

The signed detour will send drivers onto N.C. 711, Redmond Road, Deep Branch Road, Three Bridges Road and U.S. 74 Alternate. Drivers should be alert for crews and equipment, and allow for extra time during their commute.

During the closure, workers will remove the existing traffic signal and some of the asphalt, as well as grade, pave and install concrete curbs, and place a new culvert pipe underneath N.C. 710. 

Construction began in July, after the N.C. Department of Transportation awarded a $3 million contract. Construction is expected to be complete by next summer.

Roundabouts improve safety by requiring drivers to slow down and move in one direction as indicated by signs and pavement markings around the circle, which will have a raised concrete island. They also improve traffic flow by eliminating the need to stop and wait at a red light.

Ico insights

INSIGHTS

SPONSORS' CONTENT

In The Current Issue

Editor's note: Happy Mother's Day

Photo provided by magnific.comWith Mother’s Day coming up this weekend, I’d like to give a shoutout to my wonderful mom, who has done so much to shape me into the person I am today. My mom, Jeanne Meador, is a brilliant example of a selfless, in


Mental health milestone: FSU celebrates $1.45M investment in student mental health and accessibility

At center, Chancellor Darrell T. Allison and Juanette Council, Ed.D., vice chancellor for student affairs, cut the ribbon to celebrate the grand reopening of Fayetteville State University's newly renovated Spaulding Building, joined by campus leaders


A hub for innovation: FCEDC repurposes landmark Fayetteville building into a future-focused hub

FCEDC has officially moved its staff and operations to 611 W. Russell St. The 35,800- square-foot center was previously home to Homemakers Furniture and Interiors. Renovations began in the fall of 2025 and are expected to be completed in the next six to eight months. Currently, FCEDC staff are working within an open 7,500-square-foot floor plan as initial improvements progress.