Committee moves redesigned Crown Event Center forward

By Staff Report, posted 1 year ago

The Cumberland County Board of Commissioners Crown Event Center Committee gave their approval Tuesday, Jan. 23, of a revised building program and conceptual design for the new Crown Event Center, which will be constructed in Downtown Fayetteville and will replace the existing Crown Theatre and Arena.

Tuesday’s meeting followed another meeting last week, during which the Crown Event Center Project Delivery Team (PDT) presented an updated program and project cost in excess of the building program and project budget the Cumberland County Board of Commissioners approved in May 2023. During the Schematic Design and Design Development process that followed Conceptual Design, the building program increased from 131,500 square feet to 156,000 square feet and the estimated cost increased from the approved total project budget of $131.7 million to $163.5 million..

Last week, the Crown Event Center Committee directed the PDT to present a redesigned facility within a total project budget of $145 million by Monday at 1 p.m. County staff have confirmed that a total project cost of $145 million would be fully supported by the Crown Financial Model, which is funded through a combination of occupancy taxes, the food and beverage tax and revenue generated by the Crown facilities, without any assistance from General Fund tax revenue.

During Tuesday’s meeting, the PDT presented the revised Conceptual Design, which Matt DeSilver, Area Manager of MBP Carolinas, said had an estimated total project cost of $144.4 million. In addition, DeSilver said the PDT’s goal was to maintain the majority of the building program from the previously approved Conceptual Design, which includes various elements designed to generate operating revenue through concessions and VIP spaces.

DeSilver said the revised program of 134,000 square feet includes most of the major building components including capacity of almost 3,000 seats in the main event hall, luxury box suites, a VIP lounge area and a large multi-purpose room with two additional meeting rooms. The revised program required reconfiguring a number of spaces in the facility, and removed a Speakeasy bar for VIP guests, as well as a rooftop terrace. Bill Koonz, Regional Director with Project Architect EwingCole, presented the Committee with several Conceptual Design renderings of the revised program.

Committee members said they were pleased with the redesigned facility and noted that the smaller building footprint will allow for more green space around the facility, which was something they had previously requested.

“This is still an impressive building,” said Commissioner Jimmy Keefe in a press release. “I’m not really seeing anything that takes away from the customer experience, and I like that we were able to keep the same capacity, which helps keep ticket prices down.”

The Committee authorized the PDT to continue moving forward with the redesigned facility, but directed the team to try to add the rooftop terrace back into the program while maintaining the $145 million total project budget. DeSilver said the team would continue working to expedite the remaining design and construction process as well.

Ico insights

INSIGHTS

SPONSORS' CONTENT
fayetteville-state-university sambit-bhattacharya-phd headshott

FSU students and faculty make strides towards advancement in applied AI in the Intelligent Systems Laboratory

Sambit Bhattacharya, Ph.D. - Professor of Computer Science and Director of the Intelligent Systems Lab, Fayetteville State University
north-carolina-military-business-center bill-simons headshott

Federal Food Series Webinars Will Connect North Carolina Food Businesses with Government Buyers

Bill Simons - Regional Program Manager, Goldsboro, North Carolina Military Business Center
cape-fear-valley-health daniel-mccullough-md headshott

Navigating weight loss: Insights from a bariatric surgeon

Daniel McCullough, MD - Metabolic and Bariatric Surgery Director, Cape Fear Valley Health

In The Current Issue

Creating opportunities: The Defense Alliance Foundation seeks to strengthen the local defense innovation ecosystem

DAF Chairman Phil Williams (far left) pictured with City of Fayetteville Mayor Mitch Colvin (center) on June 10 following a presentation on a 25- year vision for the city’s continued growth and transformation. Photo provided by the DAF.The Defense Al


Empowering the mission: Linchpin Solutions provides tools to turn the tech of the future into the tools of today

Linchpin Solutions attends defense conferences throughout the year, using conferences and tradeshows to exhibit their services and connect with network professionals, including industry, military and government leaders to address and understand today


Lumberton is ready for takeoff: Lumberton Regional Airport embarks on major expansion to meet growing demand

Photo provided by Gary Lewis.The City of Lumberton is moving forward with a new terminal project at the Lumberton Regional Airport. It’s a collaborative effort involving several partners, including Cooper Tacia General Contractors, Talbert & Brig