
The Cumberland County Board of Commissioners Crown Event Center Committee gave their approval Tuesday, Jan. 23, of a revised building program and conceptual design for the new Crown Event Center, which will be constructed in Downtown Fayetteville and will replace the existing Crown Theatre and Arena.
Tuesday’s meeting followed another meeting last week, during which the Crown Event Center Project Delivery Team (PDT) presented an updated program and project cost in excess of the building program and project budget the Cumberland County Board of Commissioners approved in May 2023. During the Schematic Design and Design Development process that followed Conceptual Design, the building program increased from 131,500 square feet to 156,000 square feet and the estimated cost increased from the approved total project budget of $131.7 million to $163.5 million..
Last week, the Crown Event Center Committee directed the PDT to present a redesigned facility within a total project budget of $145 million by Monday at 1 p.m. County staff have confirmed that a total project cost of $145 million would be fully supported by the Crown Financial Model, which is funded through a combination of occupancy taxes, the food and beverage tax and revenue generated by the Crown facilities, without any assistance from General Fund tax revenue.
During Tuesday’s meeting, the PDT presented the revised Conceptual Design, which Matt DeSilver, Area Manager of MBP Carolinas, said had an estimated total project cost of $144.4 million. In addition, DeSilver said the PDT’s goal was to maintain the majority of the building program from the previously approved Conceptual Design, which includes various elements designed to generate operating revenue through concessions and VIP spaces.
DeSilver said the revised program of 134,000 square feet includes most of the major building components including capacity of almost 3,000 seats in the main event hall, luxury box suites, a VIP lounge area and a large multi-purpose room with two additional meeting rooms. The revised program required reconfiguring a number of spaces in the facility, and removed a Speakeasy bar for VIP guests, as well as a rooftop terrace. Bill Koonz, Regional Director with Project Architect EwingCole, presented the Committee with several Conceptual Design renderings of the revised program.
Committee members said they were pleased with the redesigned facility and noted that the smaller building footprint will allow for more green space around the facility, which was something they had previously requested.
“This is still an impressive building,” said Commissioner Jimmy Keefe in a press release. “I’m not really seeing anything that takes away from the customer experience, and I like that we were able to keep the same capacity, which helps keep ticket prices down.”
The Committee authorized the PDT to continue moving forward with the redesigned facility, but directed the team to try to add the rooftop terrace back into the program while maintaining the $145 million total project budget. DeSilver said the team would continue working to expedite the remaining design and construction process as well.
Nearly 80 acres of commercial development are now underway in Hope Mills. With Target serving as the anchor tenant, Camden Commons will bring a dynamic mix of retail and commercial opportunities. Land clearing and grading are underway at the site dev
GRAPHIC PROVIDED BY BETTER BUSINESS BUREAUIn the fall of 2025, I was approached to be a judge for the Better Business Bureau’s 2026 award series. Like many of you in the community, I didn’t realize that the BBB had its own awards, and I was excited t
As the director of the FSU HUB, Dr. Tamara Colvin is responsible for strategic and operational leadership to provide impactful support to emerging entrepreneurs and existing small businesses. Photo provided by Colvin.Fayetteville Cumberland Regional