The Cumberland County Board of Commissioners Crown Event Center Committee recently gave its approval to allow the project to move into the Construction Document development phase.
The approval followed the presentation of updated pricing for the project from the Construction Manager at Risk (CMaR) TA Loving/Metcon. The CMaR conducted pricing on the 100% design development documents completed by project architect EwingCole, which were presented to the Committee on May 20.
Matt DeSilver, Area Manager with MBP Carolinas, which serves as the County’s Owners Representative for the project, shared that the 100% Design Development cost estimate for construction came in just above the Board’s approved construction budget of $117,864,211 at $122,173,918. However, he noted that this estimate includes built-in design escalation costs through the midpoint of construction as well as design contingency.
DeSilver said the Project Delivery Team conducted value engineering to bring the estimated construction cost down below the approved budget to $117,194,895. Items that were removed from the estimate as part of the value engineering process included an operable partition in the multipurpose room, interior window blinds, reduction of LED exterior signage and upper-level audience divider curtains in the main event hall. DeSilver said these items will still be priced so they can be included in the project in the event costs ultimately come in lower than the approved budget.
Committee members voted unanimously to approve the 100% design development cost estimate and to authorize the Project Delivery Team to move into construction document development.
The Cumberland County Board of Commissioners previously approved a total project budget of nearly $145 million in February. DeSilver said the project is still on schedule to break ground in September 2024 with anticipated completion in early 2027. He said next steps for the project will include the development of construction documents and preparation of the early site package.
Additionally, Ryan Parker with Metcon announced the CMaR will host an outreach event for subcontractors, suppliers and vendors interested in participating in the Crown Event Center project this Thursday, June 20 from 3 to 5:30 p.m. at the FSU HUB. For more information, contact 910-521-8013.
Nearly 80 acres of commercial development are now underway in Hope Mills. With Target serving as the anchor tenant, Camden Commons will bring a dynamic mix of retail and commercial opportunities. Land clearing and grading are underway at the site dev
GRAPHIC PROVIDED BY BETTER BUSINESS BUREAUIn the fall of 2025, I was approached to be a judge for the Better Business Bureau’s 2026 award series. Like many of you in the community, I didn’t realize that the BBB had its own awards, and I was excited t
As the director of the FSU HUB, Dr. Tamara Colvin is responsible for strategic and operational leadership to provide impactful support to emerging entrepreneurs and existing small businesses. Photo provided by Colvin.Fayetteville Cumberland Regional