Crown Event Center moves into Construction Document phase

By Staff Report, posted 4 months ago

The Cumberland County Board of Commissioners Crown Event Center Committee recently gave its approval to allow the project to move into the Construction Document development phase.

The approval followed the presentation of updated pricing for the project from the Construction Manager at Risk (CMaR) TA Loving/Metcon. The CMaR conducted pricing on the 100% design development documents completed by project architect EwingCole, which were presented to the Committee on May 20.

Matt DeSilver, Area Manager with MBP Carolinas, which serves as the County’s Owners Representative for the project, shared that the 100% Design Development cost estimate for construction came in just above the Board’s approved construction budget of $117,864,211 at $122,173,918. However, he noted that this estimate includes built-in design escalation costs through the midpoint of construction as well as design contingency.

DeSilver said the Project Delivery Team conducted value engineering to bring the estimated construction cost down below the approved budget to $117,194,895. Items that were removed from the estimate as part of the value engineering process included an operable partition in the multipurpose room, interior window blinds, reduction of LED exterior signage and upper-level audience divider curtains in the main event hall. DeSilver said these items will still be priced so they can be included in the project in the event costs ultimately come in lower than the approved budget.

Committee members voted unanimously to approve the 100% design development cost estimate and to authorize the Project Delivery Team to move into construction document development.

The Cumberland County Board of Commissioners previously approved a total project budget of nearly $145 million in February. DeSilver said the project is still on schedule to break ground in September 2024 with anticipated completion in early 2027. He said next steps for the project will include the development of construction documents and preparation of the early site package.

Additionally, Ryan Parker with Metcon announced the CMaR will host an outreach event for subcontractors, suppliers and vendors interested in participating in the Crown Event Center project this Thursday, June 20 from 3 to 5:30 p.m. at the FSU HUB. For more information, contact 910-521-8013.

Ico insights

INSIGHTS

SPONSORS' CONTENT

In The Current Issue

Storied home starts new chapter: Historic Fayetteville home gets renewed purpose as local business owners prepare to set up shop in the old house

The nearly 200-year-old historic Taylor-Utley House in Fayetteville is being renovated by local business owners Casey and Carl Benander to serve as the storefront for their company Haymount Homes LLC and Casey’s new physical therapy and dry needling


Honoring legacy & sacrifice: The U.S. Army Airborne and Special Operations Museum stands as a reminder of the area's military service and history

The ASOM’s annual Field of Honor, brought to you by the ASOM and the Cool Spring Downtown District, is on display through Nov. 11. Each flag comes with its own story and displays a tag identifying both the person who sponsored the flag and the flag h


Let’s celebrate! Coldwell Banker Advantage of Fayetteville holds celebration to commemorate 50 years in business

To highlight this golden anniversary, CBA hosted a gala on Sept. 12, 2024. Realtors from across the company gathered at the Carolina Barn at McCormick farms for drinks, dinner and to hear from leadership. Graphic provided by CBA.Coldwell Banker Advan